Order of work is as follows:

  1. Clean and remove old fitting
  2. remove paint from hull (nitromores)
  3. created jig to hold hull shape during rebuild
  4. remove deck ply
  5. remove varnish from inside
  6. remove transom, make new one and replace
  7. repair hull delamination
  8. remove centre board case
  9. make new centre board case
  10. insert new case and align
  11. remove tanks
  12. insert new foredeck struts and then remove old
  13. remove old side decks
  14. insert new deck ply, thwart etc
  15. seal with epoxy
  16. flat board the hull, sand, sand and sand some more!
  17. fair keel band and stringers
  18. seal with epoxy
  19. Hibuild and sand again
  20. Repaint black and sand
  21. Varnish inside
  22. refit and go sailing!